top of page

Estimate costs

Planing

 

Cost estimates are a prediction that is based on the information known at a given point in time. Cost estimates include the identification and consideration of costing alternatives to initiate and complete the project. Cost trade- offs and risks should be considered, such as make versus buy, buy versus lease, and the sharing of resources in order to achieve optimal costs for the project.

 

Cost estimates are generally expressed in units of some currency (i.e., dollars, euros, yen, etc.), although in some instances other units of measure, such as staff hours or staff days, are used to facilitate comparisons by eliminating the effects of currency fluctuations.

 

Cost estimates should be reviewed and refined during the course of the project to reflect additional detail as it becomes available and assumptions are tested. The accuracy of a project estimate will increase as the project progresses through the project life cycle. For example, a project in the initiation phase may have a rough order of magnitude (ROM) estimate in the range of −25% to +75%. Later in the project, as more information is known, definitive estimates could narrow the range of accuracy to -5% to +10%. In some organizations, there are guidelines for when such refinements can be made and the degree of confidence or accuracy that is expected. 

 

 

 

 

 

Project management plan

 

Human resource management plan

 

Scope baseline

 

Project schedule

 

Risk register

 

Enterprise environmental factors

 

Organizational process asset

 

 

Inputs:

Outputs:

Activity cost estimates

Basis of estimates

Project documents updates

downloud

Tools & techniques:

Group decision making techniques
Reserve analysis
Tree-point estimating
Parametric estimating
Analogous estimating
Expert judgment
Bottom-up estimating
Cost of quality
Project management software
Vendor bid analysis
bottom of page